Flood Zone Build Checklist
Print this page and keep it with the file for any lot in an inland A zone, which is a mapped high-risk flood area whose flood letter starts with A. Each row names who to call, the document that closes the step, and where our guide explains it.
This checklist follows the guide for one- and two-family homes in inland A zones. Coastal V zones, Coastal A zones and manufactured homes have their own rules and are not covered.
The lot
- Address: ______________________________________________
- Current FIRM (Flood Insurance Rate Map) panel number: ______________ Effective date: ______________
- BFE (base flood elevation): ______________ Required freeboard (extra height above the BFE): ______________
- Floodplain development permit number: ______________
| Done | Step | Who to call | Document that closes it | Guide |
|---|---|---|---|---|
| ☐ | Step 0: customer told the lot is mapped and what it means: map panel, BFE, permit and insurance | Local floodplain office | Address checked on the Federal Emergency Management Agency’s (FEMA) Flood Map Service Center, floodplain office called, blanks above filled in | Step 0 |
| ☐ | Step 1: current flood map pulled, and pulled again before design and before the permit | FEMA’s Flood Map Service Center, then the floodplain administrator, to ask whether a map update is pending | Current effective FIRM panel, with panel number and date | Step 1 |
| ☐ | Step 2: local permit started, since it governs everything after it | Floodplain administrator | Floodplain development permit | Step 2, Part 7 |
| ☐ | Step 3: surveyor hired; staking the BFE on site is recommended | Licensed surveyor | BFE stake, and the elevation certificate (EC) at the stage the jurisdiction requires | Step 3 |
| ☐ | Step 4: floor height set at the BFE plus the local freeboard, with the subdivision plan read too | Floodplain administrator | Freeboard number in the blanks above | Step 4 |
| ☐ | Design: foundation wall height, crawlspace depth, vents, stairs and equipment worked out from the floor height before the plan is final | Floodplain administrator, and an engineer if the design calls for one | Foundation plan reviewed with the permit | Part 6 |
| ☐ | Step 5: materials below the BFE chosen to hold up in floodwater, with flood openings planned and mechanical equipment, including outdoor units and garage equipment, located to meet local rules | Floodplain administrator | Confirmed with the floodplain administrator that materials below the BFE, flood openings and equipment location meet the local rules | Step 5, equipment |
| ☐ | Step 6: any fill planned with the jurisdiction, because fill is regulated and does not change the map by itself | Floodplain administrator | Local approval for any fill, confirmed with the floodplain administrator | Step 6 |
| ☐ | Step 7: septic tank anchored against floating | Licensed septic designer and the local permitting office | Tank anchoring detail | Step 7 |
| ☐ | Step 8: end of construction closed out | Licensed surveyor and the floodplain administrator | Final (as-built) EC | Step 8 |
| ☐ | Insurance: quote in hand before the customer commits, since meeting code does not set the price | Insurance agent | Quote, with the EC | Insurance |
No BFE printed on the map? Ask the floodplain administrator how the elevation is set. Basements and the 50 percent rule for remodels are in the full guide.
Read the full guide. A SiteFacts Report flags the mapped flood zone on a lot, but it does not survey, prepare an EC, or set the floor height. Flood rules change and vary by jurisdiction, so confirm each step with your local floodplain administrator.